Grid Information

Information on Entry points, rules of grid access and physical flows.

Point Name

Dornum

Network operator

jordgasTransport GmbH

Market area

GASPOOL

Adjacent network operator

Gassco AS

Direction

Entry

Min. pressure

83,20 bar

Max. pressure

84,00 bar

Gross calorific value:

11,5 kWh/m³

Information on technical capacity

The information on the technical capacity of the entry point result from its historic use and on the application of a statistical capacity model.

Grid connection guidelines:

The connection guidelines of Open Grid Europe GmbH (OGE) apply for the pipeline subsection from Dornum to Wardenburg (Open Grid Europe) and the guidelines of Gasunie Deutschland Transport Services GmbH (GUD) apply for the pipeline subsection from Wardenburg to Steinitz (Gasunie Deutschland).